​First choice: CRT stru​cture tariff 1​


​​​​
​​​​
​​
​CRT Structure 2021
CRT component​ChargeType of ChargeCalculation of charge​
BSTtSee table (1) below​
Energy

The cost of purchasing energy from Oman Power 

and Water Procurement Company SAOC (OPWP). Defined as Bulk Supply Tariff (BSTt)

Applied to hourly kWh consumption ​

Tt
  •  Tt for the year

     = sh(1)+ sh(2)+sh(3)   x16.630 RO
                    3

  • where (sh) refers to: Snapshot

  •  Monthly Tt = Tt for the year / 12 months.
Demand
  • Transmission use of system charge is a demand charge based on customers’ contribution to the transmission network’s average system peak also known as Maximum Transmission System Demand (“MTSD”). MTSD is calculated as an average across three snapshots during which total system demand is at its highest (with the three snapshots at least 21 days apart). Peak hours are normally achieved during the summer period.​
Dt
(4) Bz/KWH for premises connected to 33KV network level, (5) Bz/KWH for premises connected to 11KV network level, (11) Bz/KWH for premises connected to 0. 415KV network level
Energy
The charges for using the distribution network that delivers electricity from the transmission substation to customers’ premises. Customers connected on the transmission network WILL NOT PAY Distribution Charges, as they do not use the distribution network. 
St50 RO/customerStanding
The cost of meter reading, billing, collection and other services provided to the customer. This is a flat fee per customer, regardless the annual consumption.

​​

​Cost Reflective Tariff (CRT) = Bulk Supply Tariff (BSTt) + (Transmission Tariff Charges (Tt) + Distribution Charges (Dt) + Supply Charges (St)

Where BSTt is the cost of energy charged at the electricity Bulk Supply Tariff in year;
Tt is a transmission use of system charge
Dtis a distribution use of system charge
Stis a charge for the administrative costs of Supply
  • ​​​ January-March
    • Off-Peak
    • 02:00 - 11:59
    • 16:00 - 21:59
  • 12
    • Night- Peak
    • 01:59 - 22:00
  • 12
    • Day Peak (Sun-Thu)
    • 12:00 - 15:59
  • 12
    • Weekend Peak (Fri-Sat)
    • 12:00 - 15:59​
  • 12
  • April
    • Off-Peak
    • 02:00 - 11:59
    • 16:00 - 21:59
  • 15
    • Night- Peak
    • 01:59 - 22:00
  • 15
    • Day Peak (Sun-Thu)
    • 12:00 - 15:59
  • 15
    • Weekend Peak (Fri-Sat)
    • 12:00 - 15:59
  • 15
  • May-July
    • Off-Peak
    • 02:00 - 11:59
    • 16:00 - 21:59
  • 18
    • Night- Peak
    • 01:59 - 22:00
  • 26
    • Day Peak (Sun-Thu)
    • 12:00 - 15:59
  • 67
    • Weekend Peak (Fri-Sat)
    • 12:00 - 15:59
  • 37
  • August- September
    • Off-Peak
    • 02:00 - 11:59
    • 16:00 - 21:59
  • 18
    • Night- Peak
    • 01:59 - 22:00
  • 24
    • Day Peak (Sun-Thu)
    • 12:00 - 15:59
  • 29
    • Weekend Peak (Fri-Sat)
    • 12:00 - 15:59
  • 22
  • October
    • Off-Peak
    • 02:00 - 11:59
    • 16:00 - 21:59
  • 15
    • Night- Peak
    • 01:59 - 22:00
  • 15
    • Day Peak (Sun-Thu)
    • 12:00 - 15:59
  • 15
    • Weekend Peak (Fri-Sat)
    • 12:00 - 15:59
  • 15​​
  • November-December
    • Off-Peak
    • 02:00 - 11:59
    • 16:00 - 21:59
  • 12
    • Night- Peak
    • 01:59 - 22:00​
  • 12
    • Day Peak (Sun-Thu)
    • 12:00 - 15:59​
  • 12
    • Weekend Peak (Fri-Sat)
    • 12:00 - 15:59
  • 12
​ ​​​Table(1)​




Second choice: Fixed sessional tariff according to the level of loads ​​


​​​​
 
Tariff type (HT) 132 KV network level,​ ​220 KV 400 KV​33KV network level & 11 KV 0.415 KV network level (LT)
​​Winter tariff (1st October to 30th April​) 17 Bz/KWH​ 22 Bz/KWH 25 Bz/KWH
​ Summer tariff (1st May to 30th September) 30 Bz/KWH 35 Bz/KWH 38 Bz/KWH