​​​​​​​​​​​​​​​When making a new modification in your current premise or add another equipment to your premise, in you have to make sure that the current connected load is sufficient to the modifications done. If you are not sure about the sufficiency of connected load with your new requirements, you can visit any of our offices and get an advice from our engineers on the way forward.​

Required documents for additional load (enlarge meter size):

  1. Copy of ID
  2. Copy of Mulkiya and krooki
  3. Modification permit  (from Ministry of Municipalities) in case building is modified.
  4. Copy of the permit from Electricity engineer who is responsible for the internal electricity connections
  5. Description of the additional devices/appliances required to be connected and their required load

Required process for additional load request​:

  1. Visit any of your nearest Sanad Centers with required documents & submit your request.
  2. After receiving the required documents, the inspector will visit the site, inspect the safety of the connections, and propose the best solution to connect to electrical source.
  3. The customer will pay connection fees & required load (if applicable). An account will be created for the customer in order to be able to make payment of charges for new connection as well as receive monthly electricity bills.
  4. You will then be given a list of approved companies that will be able to install the new meter (which is previously inspected by us) and connecting to the power source.
  5. Mazoon Electricity will then perform the final safety check to ensure that all connections are in place and are safe for use.