​​​​​​​​​​​Initial Connection request

Is where the customer requests for electricity connection while starting the construction process and after receiving the no objection letter from municipality to be able to enhance the network if required.

Required documents for Initial Connection:

  1. Copy of ID
  2. Copy of Mulkiya and Krooki
  3. No objection certificate from municipality
  4. Copy of the permit from Electricity engineer who will be responsible for the internal electricity connections
  5. Type of load required

Required process for New Connection request:

  1. Visit any of your nearest Sanad service center to apply for the service
  2.  After receiving the required documents, the inspector will visit the site, inspect the safety of the connections, and propose the best solution to connect to electrical source.
  3. The company will be able to enhance the network if required.